Permits are the part of a remodel homeowners can’t see, and the part that most often decides when work can actually start. In Palm Beach County, how long a permit takes depends on three things: who issues it, what kind of work it covers, and how complete the application is the first time.

Florida law now sets firm review deadlines for many residential permits, and the rules changed again on July 1, 2026. This guide explains the current timelines, how they apply to kitchens, bathrooms, additions and condos, and how to keep your permit from becoming the bottleneck.

Key Takeaways

Who issues your permit

Palm Beach County has dozens of municipalities, and most run their own building departments. If your home is inside Boca Raton, Delray Beach, Boynton Beach, West Palm Beach or another city, that city issues your permit. If you are in an unincorporated area, the county’s Planning, Zoning and Building Department does. Each one has its own portal, forms and inspection scheduling, but all of them follow the same state review deadlines.

Florida’s permit review deadlines

Florida Statute 553.792 requires local governments to approve, approve with conditions, or deny a complete permit application within set timeframes (Fla. Stat. 553.792). HB 803, which took effect July 1, 2026, added a faster track for smaller single-family jobs (City of Miami summary).

Permit typeReview deadlineApplies to
Existing single-family home, work under $15,0005 business daysStructural, electrical, plumbing, mechanical, gas, roofing and similar permits
Single-family home under 7,500 sq ft30 business daysBuilding and trade permits for the home
Homes 7,500 sq ft or larger, multifamily up to 50 units60 business daysLarger homes and many condo buildings
Corrections after a comment noticeYou have 10 business days to respond; the department then has 10 business daysApplications that receive review comments

Two details matter. First, the clock runs from a complete and sufficient application, so missing documents mean the clock never starts. Second, applicants can waive the deadlines in writing, and some departments ask for that waiver when a project needs more back-and-forth.

What HB 803 changed in 2026

Typical permit timelines by project

These ranges reflect common experience across Palm Beach County jurisdictions. Your project may move faster or slower depending on the department’s workload and whether reviewers send comments.

ProjectTypical permitsWhat to expect
Kitchen remodel, same layoutBuilding, electrical, plumbingOften a few days to a few weeks; smaller jobs may qualify for the 5-day track
Bathroom remodel or tub-to-shower conversionPlumbing, electrical, sometimes buildingOften a few days to a few weeks
Condo kitchen or bathBuilding and trade permits plus association approvalAssociation review commonly adds several weeks before the permit is filed
Wall removal or open-concept remodelBuilding with structural drawings, trade permitsSeveral weeks, since engineered drawings are reviewed
Home additionBuilding with signed and sealed plans, zoning review, tradesOften one to three months, plus survey and design time

Boca Raton, for example, does not offer paid expedited plan review (City of Boca Raton FAQ), so a complete submission and quick responses to comments are what keep things moving.

North2South owner reviewing tile samples in a showroom
Selections and drawings finished before the permit is filed mean fewer revisions once review starts.

Not sure what permits your project needs?

North2South Renovations handles permits, inspections and condo or HOA approvals for every project we build.

Get a Free EstimateCall (561) 664-3256

The permit process, step by step

  1. Scope and drawings

    The contractor defines the work and prepares drawings. Structural changes and additions need signed and sealed plans from an engineer or architect.

  2. Association approval (if applicable)

    Condos and many HOA communities review the work. Condo approval letters are often part of the permit application.

  3. Application and intake

    The application, drawings, product approvals and fees are submitted through the city or county portal and checked for completeness.

  4. Plan review

    Reviewers check the plans against the Florida Building Code. If they have comments, the applicant revises and resubmits.

  5. Permit issued and Notice of Commencement

    The permit is issued. For contracts over $5,000, a recorded Notice of Commencement must be posted before the first inspection.

  6. Inspections

    Rough, in-progress and final inspections are scheduled as the work reaches each stage.

  7. Final inspection and close-out

    The final inspection closes the permit, which protects you when you sell or insure the home.

How to keep your permit from delaying your remodel

How North2South handles permits

North2South Renovations is a state-certified building contractor (License #CBC1269429). We prepare the applications, coordinate drawings with architects and engineers when needed, respond to plan review comments, schedule inspections and handle condo and HOA approvals across Palm Beach County. Learn more about our permits and HOA/condo approvals service, or see how permits fit into a kitchen remodel checklist and a bathroom remodel timeline.

Frequently Asked Questions

How long does it take to get a building permit in Palm Beach County

It depends on the project and the jurisdiction. Florida law requires a decision within 30 business days on a complete application for a single-family home under 7,500 square feet, and within 5 business days for work under $15,000 on an existing single-family home. Simple remodel permits often come back faster.

Do I need a permit to remodel my kitchen or bathroom

Usually yes. Electrical, plumbing, mechanical, gas and structural work all need permits. Florida’s $7,500 exemption only covers small single-family jobs that don’t include those trades.

Does the 5-day permit deadline apply to condos

No. The 5-business-day track that took effect July 1, 2026 applies to existing single-family dwellings with work valued under $15,000.

What happens if the city misses the deadline

Florida law includes consequences for missing review deadlines, such as fee reductions or, in some cases, permits deemed approved. Applicants can also waive the deadlines in writing, so ask your contractor how your department handles it.

Who pulls the permit, me or my contractor

Your licensed contractor normally pulls the permit and is responsible for the inspections. Owner-builder permits are possible for some single-family work, but the owner then takes on the contractor’s legal responsibilities.